Works are far advanced with the site manager Edward Nyarko disclosing the project is 84% complete and will be handed over to National Youth Authority at the end of April, your most reliable source, Domesticsportsgh.com can exclusively confirm.
The Multi sports facility will host sporting events including Football, Athletics, Basketball, and long tennis.
The project is made of four seating stands, which includes 35- seater VIP/ Presidential lounge, General seating areas, Media Tribune, Control room for media and stadium operations, Dressing room for players of two teams with 26 locker rooms each, referees rooms for 6 officials and multiple purpose courts for Hand sports such as Basket ball, Handball, Long Tennis and volley ball.
According to report by the National Youth Authority, the current expenditure of the Axim Youth Resource Centre stands at ยข18million cedis( $1.46m Dollars).